SCHEDULE CERTAINTY THAT PROTECTS REVENUE

Akordi finalist in the AFR BOSS Innovative Companies 2025

The Challenge A Client preparing to deliver a high-stakes road and earthworks megaproject needed independent validation of their delivery plan before construction, with substantial delay penalties at risk.

The Approach After months of traditional planning, Akordi stepped in to apply expert-led AI-enabled schedule optimisation using a suite of tools to validate the baseline and strengthen resilience, identifying opportunities for on-time delivery confidence.

The Impact

  • 56 days total impact: 23 days schedule reduction + 33 days added contingency
  • 20% improvement in piling efficiency
  • 4x return on investment
  • $2.8M in liquidated damages avoided through early error detection
  • 43% reduction in concrete defect rates

Related Resources

Article Link

Digital Risk Intelligence: Preventing 10-Month Project Delay

Sep 22, 2025
Case Studies
Article Link

Infrastructure Transmission: Optimising 800 MW Project Delivery

Sep 22, 2025
Case Studies
Article Link

Renewable Energy: Building Resilience in Wind Farm Delivery

Sep 22, 2025
Case Studies
Article Link

Mining & Resources: Unlocking 5.4% Project Cost Savings with Generative Scheduling

Sep 22, 2025
Case Studies
Button Text